← Library
Patna High CourtCWJC/743/2025disposed

Softpro India Computer Technologies Private Limited v. The Lalit Narayan Mithila University,

2025-12-15Mr. Justice Anil Kumar Sinha3 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.743 of 2025 ====================================================== Softpro India Computer Technologies Private Limited a company incorporated with Corporate Identity Number U74900UP2010PTC039243 under the provisions of the Companies Act, having its registered office at 533/69 Mahaveer Ji ka Purwa, Kapoorthala, Aliganj, Lucknow- 226606, Uttar Pradesh through its Chief Executive Officer (CEO) Yashi Asthana, aged 37 years, female, daughter of Kuldeep Asthana, resident of C-9/631, Insaf Nagar, Sector- 10, Indira Nagar, Lucknow- 226016, Uttar Pradesh. ... ... Petitioner/s

Versus

1.

The Lalit Narayan Mithila University, Kameshwarnagar, Darbhanga through its Registrar.

2.

The Vice Chancellor, The Lalit Narayan Mithila University, Kameshwarnagar, Darbhanga.

3.

The Registrar, The Lalit Narayan Mithila University, Kameshwarnagar, Darbhanga.

4.

The Finance Officer, The Lalit Narayan Mithila University, Kameshwarnagar, Darbhanga.

5.

The Finance Advisor, The Lalit Narayan Mithila University, Kameshwarnagar, Darbhanga.

... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr. Anjani Kumar, Sr. Advocate Mr. Gyan Prakash, Advocate For the University :

Mr. Bindhyachal Rai, Advocate For the Intervenor :

Mr. Jagnnath Singh, Advocate Mr. Padmanabh Kashyap, Advocate Mr. Deepak Kumar, Advocate Mr. Md. Ghulam Mustafa, Advocate ====================================================== CORAM: HONOURABLE MR. JUSTICE ANIL KUMAR SINHA ORAL ORDER 15-12-2025 Heard Mr. Anjani Kumar, learned senior counsel for the petitioner along with Mr. Gyan Prakash, Advocate, Mr. Bindhyachal Rai, learned counsel for the University and Mr. Jagnnath Singh, learned counsel for the Intervenor.

2. The petitioner has filed the present writ application for a direction to the University to pay the bills of Annual

Patna High Court CWJC No.743 of 2025(11) dt.15-12-2025 2/3 Maintenance Cost of the College Automation System Software under the Enterprise Resource Planning (ERP) for 43 constituent Colleges of the Lalit Narayan Mithila University, Darbhanga.

3. According to the petitioner, the University advertised tender for the college automation work under the Enterprise Resource Planning (ERP) of the university and on evaluation of technical and financial bids, the petitioner was declared as L-1 bidder for the said work. The agreement was executed between the University and the petitioner on 11.08.2021 and Work Order was issued to the petitioner on 16.08.2021. The total value of the work of college automation system has already been paid to the petitioner. The only dispute is with regard to the payment of Annual Maintenance Cost. According to the petitioner, a sum of Rs. 5,41,79,215/- is the bill amount, out of which a sum of Rs. 88 lakhs has only been paid.

4. Learned counsel for the University submits that the verification of the work of Annual Maintenance is being done at the University level from every colleges and about 90 lakhs has been paid to the petitioner after verification of Annual Maintenance work done by it. He further submits that the process of verification may take three to four months and after

Patna High Court CWJC No.743 of 2025(11) dt.15-12-2025 3/3 proper verification of the work done by the petitioner, the payment due to the petitioner shall be made.

5. Mr. Jagnnath Singh, learned counsel for the Intervenor submits that if payment is going to be made after proper verification by the present incumbent, he has nothing to say.

6. After having heard learned counsel for the parties and taking into consideration the nature of dispute, this writ application is disposed with a direction to the Vice Chancellor to get the work done by the petitioner examined and verified properly, towards the Annual Maintenance Cost (AMC) and if the Vice Chancellor is satisfied that the petitioner has performed the work of Annual Maintenance in the colleges, then the due amount as per the agreement, shall be paid to the petitioner. The entire exercise of verification and payment, if any, is to be done within a period of four months.

7. With the aforesaid observation and direction, this writ application stands disposed of.

(Anil Kumar Sinha, J) Siwani/- U