In Re- N.H.82 Four Lane Project v. The Union Of India
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.483 of 2022 ====================================================== In Re- N.H.82 Four Lane Project Gaya- Hisua- Rajgir, Biharsharif Section. ... ... Petitioner/s
Versus
1.
The Union of India through the Secretary, Ministry of Road Transport and Highways, Government of India, New Delhi.
2.
The Secretary, Ministry of Road Transport and Highways, Government of India, New Delhi.
3.
The National Highway Authority of India, New Delhi through its Chairman, New Delhi.
4.
The Chairman, National Highway Authority of India, New Delhi. 5.
The State of Bihar, through the Chief Secretary, Government of Bihar, Patna. 6.
The Chief Secretary, Government of Bihar, Patna. 7.
The Principal Secretary, Secretary, Road Construction Department Government of Bihar, Patna.
8.
The Principal Secretary, Department of Revenue and Land Reforms, Government of Bihar.
9.
The District Magistrate, Gaya.
10.
The Secretary, Department of Economic Affairs, Ministry of finance, Government of India, New Delhi.
11.
The Bihar State Road Development Corporation Ltd., Patna. ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
For the Respondents :
Mr. P.K. Shahi, Advocate General Mr. Anjani Kumar, AAG-4 Mr. Manish Dhari Singh, A.C. to AG.
Dr. K.N. Singh, Sr. Advocate Mr. Shivaditya Dhari Sinha, Advocate Ms Prakritita Sharma, Advocate
Patna High Court CWJC No.483 of 2022 dt.28-02-2025 2/3 Mr. Amarjet, Advocate ====================================================== CORAM: HONOURABLE THE ACTING CHIEF JUSTICE and HONOURABLE MR. JUSTICE PARTHA SARTHY ORAL JUDGMENT (Per: HONOURABLE THE ACTING CHIEF JUSTICE) Date : 28-02-2025 The learned Advocate General has informed this Court that the construction of the ROB at Rajgir is completed to the extent of 86.5 percent and the expected date when the entire ROB would be constructed is 31.03.2025.
2. With respect to the ROB at Rasalpur, 73 percent of the work has been done and the rest of the work is expected to be completed by 30th of June, 2025.
3. With this updated report about the stage of construction, there would be no necessity of continuing with this case.
4. We, therefore, close this petition with the hope and trust that by the expected date, the construction
Patna High Court CWJC No.483 of 2022 dt.28-02-2025 3/3 would be completed.
5. Records consigned.
(Ashutosh Kumar, ACJ) (Partha Sarthy, J) P.K.P./- AFR/NAFR CAV DATE Uploading Date 03.03.2025 Transmission Date