← Library
Patna High CourtCWJC/800/2026disposed

Asharfi Saw v. The Union Of India And ANR

2026-01-22Mr. Justice Rajiv Roy3 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.800 of 2026 ====================================================== ASHARFI SAW LATE TULSI SAW PIRIBAZAR P.S PIRIBAZAR DISTRICT LAKHISARAI ... ... Petitioner/s

Versus

1.

The Union of India through the General Manager, Eastern Railway, Kolkata. 2.

The D.R.M. Eastern Railway, D.R.M. Office, Malda, West Bengal. 3.

The State of Bihar Through, Principal Secretary, Land and Revenue Department Bihar, Patna.

4.

The District Magistrate, Lakhsarai.

5.

The Sub-Divisional Officer, Lakhisarai Sadar, District- Lakhisarai. 6.

The Superintendent of Police, Lakhisarai.

7.

The Circle Officer, Suryagarha Anchal, District- Lakhisarai. 8.

The S.H.O., Piri Bazar, Police Station.

... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr. Mayank Bilochan, Advocate For the Respondent/s :

Mr. S. Raza Ahmad, AAG-5 Mr. Md. Kamil Akhtar, AC to AAG-5 For the UOI :

Mr. Krishna Kant Tiwari, Advocate ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJIV ROY ORAL ORDER 22-01-2026 Heard the parties.

2. The present petition has been preferred for the following relief(s):

"(i) for issuance of an appropriate writ commanding the respondents not to construct the Railway under pass, over the land of the petitioner which is Raiyti/Purchased land of the petitioner. (ii) For issuance of an appropriate writ

Patna High Court CWJC No.800 of 2026(2) dt.22-01-2026 2/3 restraining the respondents not to make any interference in the peaceful possession of the petitioner.

(iii) For issuance of an appropriate writ commanding the respondent to first acquire the land under the provision of land acquisition act and pay the compensation or vacate the land of the petitioner.

(iv) For any other relief or reliefs for which petitioner is entitled."

3. Learned counsel for the petitioner submits that the land belongs to him but the Railways without compensation, have decided to use the said land for the construction of Railway Under Pass.

4. Learned counsel representing the Union of India submits that the writ petition is bereft of supporting documents.

5. Learned counsel for the petitioner submits that it will suffice if the fresh petition preferred before the General Manager, Eastern Railways, Kolkata (respondent no. 1) is taken to its logical conclusion.

6. Learned counsel representing the Union of India has no objection to it.

Patna High Court CWJC No.800 of 2026(2) dt.22-01-2026 3/3

7. In that background, the writ petition stands disposed of allowing the petitioner to approach the concerned respondent in next four weeks. If such fresh petition is preferred in next four weeks, the concerned respondent is directed to take the matter to its logical conclusion at an earliest. (Rajiv Roy, J) Adnan/- U