IN THE HIGH COURT OF JUDICATURE AT PATNA

CRIMINAL MISCELLANEOUS No.15859 of 2021 Arising Out of PS. Case No.-84 Year-2019 Thana- KOPA District- Saran ====================================================== SHAMSHER SHAH @ SHAMSHER ALI Son of Abbas Shah R/o VillageAnwal, P.S.- Kopa, District- Saran, Chapra. ... ... Petitioner/s

Versus

THE STATE OF BIHAR ... ... Opposite Party/s ====================================================== Appearance :

For the Petitioner/s :

Mr.Manoj Kumar, Advocate For the Opposite Party/s :

Mr.Brajendra Nath Pandey, APP ====================================================== CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH ORAL ORDER 08-09-2021 Heard learned counsel for the petitioner and learned APP for the State through virtual mode.

Counsel for the petitioner is directed to remove the defect(s), as pointed out, by the office, within a period of four weeks from the date of restoration of normalcy. The petitioner seeks bail in connection with S.Tr. No.556 of 2019 arising out of Kopa P.S. case No.84 of 2019 registered under Sections 147, 148, 149, 323, 324, 307, 302, 504 of the Indian Penal Code, pending in the court of Additional District and Sessions Judge 12th, Saran at Chapra. The earlier bail application of the petitioner was rejected vide Annexure 2 to the present application taking into account that the petitioner is the assailant. A report was called for from the trial court. It has been

Patna High Court CR. MISC. No.15859 of 2021(3) dt.08-09-2021 2/2 reported that four witnesses are still to be examined by the prosecution and the trial is expected to be concluded within a period of six months.

Considering the nature of accusation and the stage of the case, I am not inclined to grant bail to the petitioner. The same is rejected.

The Trial Court is directed to take all necessary steps to conclude the trial preferably within a period of six months from the date of receipt/production of a copy of this order. (Sudhir Singh, J) Narendra/- U T