M/S Kumar Kant Constructions v. The State Of Bihar
IN THE HIGH COURT OF JUDICATURE AT PATNA
Miscellaneous Jurisdiction Case No.290 of 2024 In Civil Writ Jurisdiction Case No.17680 of 2022 ====================================================== M/s Kumar Kant Constructions through its Proprietor Shambhu Nath Choudhary, Male, aged about 74 years, son of Late Kartik Prasad Choudhary, resident of Kotwali Chowk, near Dr. Pramod Tiwari Clinic, P S Bettiah Town, District Bettiah, West Champaran, Bihar.
... ... Petitioner/s
Versus
1.
The State of Bihar through the Principal Secretary, Rural Works Department, Government of Bihar, Patna, namely Pankaj Kumar Pal, son of not known to the petitioner.
2.
The Engineer in Chief, Rural Works Department, Government of Bihar, Patna namely Amarendra Kumar Sinha, son of not known to the petitioner. 3.
The Chief Engineer-3, Rural Works Department, Government of Bihar, Patna namely Niraj Kumar, son of not known to the petitioner. 4.
The Superintending Engineer cum Nodal Officer, PMGSY BRADA, Patna namely Bhagwat Ram, son of not known to the petitioner. 5.
The Superintending Engineer, Rural Works Department, Works Circle, Sitamarhi, District Sitamarhi, Bihar, namely Bhagwat Ram, son of not known to the petitioner.
6.
The Executive Engineer, Rural Works Department, Works Division, Belsand, District Sitamarhi, Bihar, namely Rajesh Ratnakar, son of not known to the petitioner.
... ... Opposite Party/s ====================================================== Appearance :
For the Petitioner/s :
Mr. Prabhat Ranjan, Advocate For the Opposite Party/s :
Mr. Government Advocate 5 ====================================================== CORAM: HONOURABLE MR. JUSTICE P. B. BAJANTHRI and HONOURABLE MR. JUSTICE ARUN KUMAR JHA ORAL ORDER (Per: HONOURABLE MR. JUSTICE P. B. BAJANTHRI) 05-07-2024 Pursuant to our order dated 21.06.2024, supplementary show cause has been filed on behalf of opposite party nos. 1, 2, 3, 5 and 6 along with documents bearing Annexure Nos. A to H.
Patna High Court MJC No.290 of 2024(4) dt.05-07-2024 2/2
2. The Executive Engineer has taken a decision to the extent that petitioner is required to complete the allotted work on or before 31.12.2024. In the meantime, execution of certificate case has been withheld. In the light of these developments, the present MJC does not survive for consideration.
3. Accordingly, the present MJC petition stands disposed of.
(P. B. Bajanthri, J) ( Arun Kumar Jha, J) Balmukund/- Ashish/- U