← Library
Patna High CourtCWJC/9353/2017disposed

Chitranjan Sharma v. The State Of Bihar And ORS

2025-04-21Mr. Justice Rajiv Roy3 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.9353 of 2017 ====================================================== Chitranjan Sharma Son of Late Ram Dhyan Sharma, Resident of VillageSohbara, P.S.- Tekari, District- Gaya. ... ... Petitioner/s

Versus

1.

The State Of Bihar and Ors 2.

The Principal Secretary, Department of Irrigation, Government of Bihar, Patna.

3.

The Collector, Gaya.

4.

The Special Land Acquisition Officer, Sone Project, Aurangabad, DistrictAurangabad. 5.

The Circle Officer, Tekari, District- Gaya.

6.

The Arbitrator cum Divisional Commissioner, Magadh Division, Gaya ... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr.Binod Kumar, Advocate For the Respondent/s :

Mr.Vinay Kirti Singh-Ga-2 ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJIV ROY ORAL ORDER 21-04-2025 Learned counsel for the petitioner prays for and is allowed to implead the Arbitrator cum Divisional Commissioner, Magadh Division, Gaya as respondent no.6 in course of the day.

2 Heard the parties.

3. The present petition has been preferred for the following relief/s:

(i) for issuance of an appropriate writ/ writs, order/ orders, direction/ directions, commanding and directing the respondent authorities, specially the respondent no 4

Patna High Court CWJC No.9353 of 2017(2) dt.21-04-2025 2/3 the Special Land Acquisition Officer, Sone Project Aurangabad to pay the compensation amount at the rate of 4 times of the circle rate of the land fixed by the government in respect of the land of the petitioner along with statutory interest which has been acquired by the respondent authorities under sone project for construction of the Nasirna Minor Canal as the farmers of other villages have been paid compensation amount at the rate of 4 times of the circle rate but the petitioner has been paid below at the rate of circle rate. The petitioner further prays for any other relief/ reliefs for which he may be found entitled in the facts and circumstances of the present case.

4. A counter affidavit has been filed on behalf of respondent no.4 then Special Land Acquisition Officer, Aurangabad detailing out that after sanction of revised estimate, the petitioner received Rs. 1,59,662/- on 11.04.2017 and as such he has already been paid appropriate compensation.

Patna High Court CWJC No.9353 of 2017(2) dt.21-04-2025 3/3

5. The rejoinder of the petitioner shows that he still entitled to some amount.

6. Learned counsel for the petitioner submits that he shall be approaching the newly added respondent, the Arbitrator cum Divisional Commissioner, Magadh Division, Gaya for the redressal of the grievance.

7. If such petition is preferred by the petitioner, the same be taken to its logical conclusion.

8. Needless to say that if the respondent come to a conclusion that the petitioner still has some case, an appropriate order be passed.

8. With the aforesaid observation, the writ petition stands disposed of.

(Rajiv Roy, J) Ravi/- U