Mirtunjay Kaji v. The Union Of India And ORS
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.19021 of 2017 ====================================================== Mirtunjay Kaji Son of Late Jaynath Kaji, Resident of Village- Serwa, Police Station- Matiyariya, District- West Champaran at Bettiah. ... ... Petitioner/s
Versus
1.
The Union Of India 2.
The State of Bihar.
3.
The Chief Secretary, Government of Bihar, Patna. 4.
The Principal Secretary, Road Construction Department, Patna, Bihar. 5.
The District Collectoriate, West Champaran at Bettiah. 6.
The Assistant Director, Road Construction Department, West Champaran at Bettiah.
7.
The Deputy Development Commissioner, Bettiah, West Champaran. 8.
The Executive Engineer, Water Resource Commissionary, Bettiah, West Champaran.
... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr.Uday Kumar Mishra, Adv.
For the Respondent/s :
Mr.Anjani Kumar - A.A.G. -4 Mr. Shailendra Kr. Singh, AC to A.A.G. 4 For U.O.I. Smt. Nivedita Nirvikar, Adv. ====================================================== CORAM: HONOURABLE THE CHIEF JUSTICE and HONOURABLE MR. JUSTICE ANIL KUMAR UPADHYAY ORAL ORDER (Per: HONOURABLE THE CHIEF JUSTICE) 06-01-2020 The petition filed on 20.12.2017 is listed for hearing for the first time today before the Court.
Heard learned counsel for the petitioner and learned counsel for the respondents.
Petitioner has prayed for the following relief/s: "For issuance of appropriate writ, order of orders,
Patna High Court CWJC No.19021 of 2017(2) dt.06-01-2020 2/2 direction or directions to the respondents to stop Bridge making on Ganguli River, which is made on Ganguli River and it's place is 43.40 K.M. from Madanpur and 700 meter east to Matiyariya village and 500 meter west to Sirisiya Village, Police Station - Matiyariya, District - West Champaran."
The present petition filed in its present form is totally misconceived as it is definitely not in the interest of public to stop the construction of the bridge which commenced in the year 2012.
As such, we dismiss the present petition.
(Sanjay Karol, CJ) ( Anil Kumar Upadhyay, J) K.C.Jha/- U