Patna High CourtCWJC/2926/2022disposed

Vikas Kumar (Nh-85 Chhapra-Siwan- Gopalganj Section On Epc) v. The Union Of India

2022-12-13The Chief Justice -,Mr. Justice Partha Sarthy2 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.2926 of 2022 ====================================================== Vikas Kumar (NH-85 Chhapra-Siwan- Gopalganj Section on EPC) Son of Late Baleshwar Sharma Resident of Road No. 25 A, Rajiv Nagar, P.S.- Rajiv Nagar, District- Patna ... ... Petitioner/s

Versus

1.

The Union of India through the Secretary, Department of Ministry of Road Transport and Highway Authority of India, New Delhi. 2.

The Secretary, Department of Ministry of Road Transport and Highway Authority of India, New Delhi.

3.

The National Highway Authority through its Chairman. 4.

The Additional Chief Secretary, Road Construction Department, Government of Bihar, Patna.

5.

The District Magistrate, Saran.

6.

The District Magistrate, Siwan.

7.

The District Magistrate, Gopalganj.

... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr. P.K. Shahi, Amicus Curiae Mr.Vikas Kumar (In Person) For the State :

Mr. Anjani Kumar, AAG-4 Mr. Alok Kumar Rahi, AC to AAG-4 For the UOI :

Mr. Kumar Priya Ranjan, C.G.C.

For NHAI :

Dr. K.N.Singh, A.S.G.

Dr. Maurya Vijay Chandra, Advocate Mr. Devansh Shankar Singh, JC to A.S.G.

Mr. Gaurav Govinda, Advocate Mr. Rishav Ranjan, Advocate Mr. Sriram Krishna, JC to A.S.G.

Ms. Anjali Kuumari, Advocate.

Mr. Amarjeet, JC to A.S.G.

Mr. Sanat Kumar Mishra, Mr. Prabhat Kumar Singh, Advocate ====================================================== CORAM: HONOURABLE THE CHIEF JUSTICE and HONOURABLE MR. JUSTICE PARTHA SARTHY ORAL JUDGMENT (Per: HONOURABLE THE CHIEF JUSTICE) Date : 13-12-2022 In the instant petition, the Court was monitoring

Patna High Court CWJC No.2926 of 2022 dt.13-12-2022 2/2 construction of N.H.-85, Chapra-Siwan-Gopalganj Section EPC.

Dr. K.N.Singh states that entire stretch of road stands completed as also road is now fully functional and operational.

We are further informed that 500 meters of stretch of road would be completed.

We are happy to record that on account of efforts put in by all the learned counsel and more specifically, Shri P.K.Shahi, learned Amicus Curiae, construction is now complete and the road is fully functional and operational. Needless to say, the road would be maintained, as is so executed, in terms of and under the agreement entered into between the NHAI and the concessionaire/contractor. Present proceedings stands closed.

(Sanjay Karol, CJ) ( Partha Sarthy, J) Sujit/Ashwini AFR/NAFR CAV DATE Uploading Date 17.12.2022 Transmission Date