Karuna Nidhan Choudhary v. The State Of Bihar And ORS
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.4110 of 2019 ====================================================== Karuna Nidhan Choudhary S/o Late Yamuna Prasad Choudhary R/o Village and P.O.-Teghra, P.S. Haveli Kharagpur, District Munger at present Superannuated as Chainman 4th Grade Staff on 31.12.2014 under the office of the Executive Engineer, Irrigation Division, Bhagalpur at present shifted at Banka in the same capacity ... ... Petitioner/s
Versus
1.
The State of Bihar through the Principal Secretary, Department of Water Resources Sichai Bhawan, Old Secretariat Compound Bihar, Patna 2.
The Chief Engineer Irrigation Creation, Department of Water Resources, Bhagalpur 3.
The Secretary (Technical) Office of the Chief Engineer, Irrigation Creation, Department of Water Resources, Bhagalpur 4.
The Superintending Engineer Irrigation Circle, Bhagalpur, Department of Water Resources, Bhagalpur 5.
The Executive Engineer Irrigation Division, Bhagalpur at present shifted at Banka in the same capacity 6.
The Executive Engineer Irrigation Division, Banka, District Banka ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr.Kalika Nand Jha For the Respondent/s :
Mr.Vinay Kirti Singh (GA2) ====================================================== CORAM: HONOURABLE MR. JUSTICE ASHUTOSH KUMAR ORAL JUDGMENT Date : 06-03-2019 Heard the learned counsel for the petitioner and the State.
The petitioner has approached this Court for payment of difference of salary as also the arrears and payment of increments to which he is entitled and which appears to have been withheld from him without any rhyme or reason.
Patna High Court CWJC No.4110 of 2019 dt.06-03-2019 2/3 It has been submitted on behalf of the petitioner that for redressal of his grievance, viz, payment of arrears of salary and other financial benefits to which he was entitled for his having served the department for a number of years, he has filed a representation before the Executive Engineer, Irrigaiton Division, Bhagalpur (Respondent No. 5), but such representation has yielded no result.
Under the aforesaid circumstances, this Court deems it appropriate to direct the petitioner to file a fresh representation to the Chief Engineer, Irrigation Creation, Department of Water Resources, Bhagalpur (Respondent No. 2), detailing his grievance, within a period of four weeks. Should such an application be filed, the same shall be disposed off by the concerned authority, i.e., the Chief Engineer, Irrigation Creation, Department of Water Resources, Bhagalpur (Respondent No. 2), within a period of four weeks thereafter, preferably by a reasoned order. If the claim of the petitioner is found to be tenable, necessary sequel order shall be passed within the stipulated period.
Patna High Court CWJC No.4110 of 2019 dt.06-03-2019 3/3 With the aforesaid observation / direction, this petition stands disposed off.
(Ashutosh Kumar, J) skm/- AFR/NAFR N.A.F.R.
CAV DATE Uploading Date 07.03.2019 Transmission Date