← Library
Patna High CourtCWJC/2988/2015allowed

M/S Alectra Construction Ltd. Through Its Director Dhananjay Kumar v. The State Of Bihar And ORS

2015-02-27Mr. Justice Dr. Ravi Ranjan3 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.2988 of 2015 =========================================================== M/s Alectra Construction Ltd. Through Its Director Dhananjay Kumar Son of Sri Anil Kumar Singh Resident of Adarsh Nagar, New Colony, Dharampur, Samastipur, District Samastipur .... .... Petitioner

Versus

1. The State of Bihar through the Secretary, Road Construction Department, Government of Bihar, Patna.

2. The Engineer in Chief cum Additional Commissioner cum Special Director, Road Construction Department, Government of Bihar, Patna.

3. The Chief Engineer, North Bihar, Road Construction Department, Darbhanga.

4. The Superintending Engineer, Road Circle, Muzaffarpur.

5. The Executive Engineer, R.C.D. Road Division No. 1, Muzaffarpur .... .... Respondents ====================================================== Appearance :

For the Petitioner : M/s Jitendra Kumar Roy, Sumit Kumar and Rajesh Kumar, Advocates For the State : Ms. Nivedita Nirvikar, GA 10 Manoj Kumar, AC to GA 10 =========================================================== CORAM: HONOURABLE DR. JUSTICE RAVI RANJAN ORAL JUDGMENT Date: 27-02-2015 I have heard learned counsel for the petitioner and the State. Petitioner is aggrieved by the order dated 19.06.2014 contained in Annexure 1 passed by the Executive Engineer, Road Construction Department, Division No. 1, Muzaffarpur(respondent no. 5), by which the petitioner has been declared as defaulter and a bar has been imposed upon him for participation in any future tender till the work concerned is completed.

Learned counsel for the petitioner raises a short question for determination of this case.

Patna High Court CWJC No.2988 of 2015 dt.27-02-2015 It is submitted that for such debarment from future tender there are already Government Order contained in memo no. 0303/2004 2131(S) dated 13.03.2009 (Annexure 7) and Circular of the Road Construction Department, contained in letter no. 03-02/2004 818(E) dated 17.03.2009(Annexure 8). Annexure 8 clearly lays down that, before passing such order of debarment, show-cause notice should be given and after service of such notice if no reply to such show-cause notice is furnished by the contractor within 15 days then within subsequent three days an order is to be passed by the Department concerned.

It is submitted that in the present case, the show-cause notice was issued on 06.06.2014 vide Annexure 6 which was sent to the petitioner under registered cover booked on 16.06.2014 and was received by the petitioner on 18.06.2014, however, on the very next day, i.e., 19.06.2014, the impugned Annexure 1 has been passed and communicated by the authority concerned in clear violation of the Government order and its own Circular as contained in Annexures 7 and 8. Learned counsel has produced the original envelope received by him at the time of hearing of this case which establishes that letter no. 943 dated 06.06.2014 was sent to him through recovered cover booked on 16.06.2014 and was received by him at Samastipur on 18.06.2014. If it is assumed that the petitioner had received the

Patna High Court CWJC No.2988 of 2015 dt.27-02-2015 aforesaid letter on 18.06.2014 then the opportunity should have been given to file a reply to the notice within 15 days from the date of issuance of show-cause notice and in case nothing was filed then within subsequent three days the order should have been passed but in the present case on the very next day , i.e., on 19.06.2014, after receipt of the show-cause notice by the petitioner, the impugned order contained in Annexure 1 has been passed which appears to be in violation of the Annexures 7 and 8 and as such, the same cannot be sustained in law. Even if calculation is made from the date of issuance of notice then 15 days would be completed on 23.06.2014. In such a situation also, the impugned order could not have been passed on 19.06.2014.

Accordingly, this writ application succeeds and the impugned letter containing the order of debarment dated 19.06.2014 is quashed and set aside.

However, the respondent concerned would be at liberty to proceed afresh in the matter in accordance with law. (Dr. Ravi Ranjan, J) SC/- U