IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.4875 of 2016 ====================================================== Arun Kumar Sharma Son of Sri Narendra Sharma @ Nawal Kishore Sharma, Resident of Mohalla- Chandmari, Motihari, Police Station- Motihari Town, District- East Champaran.

... ... Petitioner/s

Versus

1.

The State Of Bihar and Ors 2.

The Director 'Sarva Shiksha Abhiyan' Govt. of Bihar, Patna. 3.

The Civil Work Manager Bihar Shiksha Pariyojna Parishad, Anandpuri, West Boring Canal Road, Buildin 4.

The District Magistrate cum Collector, East Champaran, Motihari. 5.

The District Programme Officer, East Champaran at Motihari. 6.

The District Education Officer, East Champaran at Motihari. 7.

The District Superintendent of Education cum District Programme Coordinator Officer, Sarva Shiksha 8.

The Assistant Engineer Cum Officer in Charge, Sarva Shiksha Abhiyan, East Champaran at Motihari.

9.

The Block Education Officer, Kalyanpur, East Champaran at Motihari. 10.

The Block Education Officer, Tetariya, East Champaran at Motihari. ... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr.Madhurendra Kumar For the State :

Mr. Gyan Prakash Ojha, GA 7 For the Respondents-BEPC Mr. Girish Kumar ====================================================== CORAM: HONOURABLE MR. JUSTICE MADHURESH PRASAD ORAL ORDER 20-06-2019 Heard counsel for the petitioner and counsel for the respondents-State.

Counsel for the petitioner submits that the petitioner would approach respondent no.8 with copy of measurement book prepared in respect of work executed under Sarva Shiksha Abhiyan Scheme for the year 2006-2007 and 2007-2008 in Kalyanpur block; and for the year 2008-2009 and 2009-2010

Patna High Court CWJC No.4875 of 2016(2) dt.20-06-2019 2/2 inTetariya block in the district of East Champaran at Motihari for payment of 2.5% remuneration for the duty performed by him as technical supervisor.

In view of such submission since decision has to be taken by respondent no.8, this proceeding need not be kept pending.

Writ petition is disposed of with liberty to the petitioner to approach respondent no.8 (The Assistant Engineercum- Officer-in-charge, Sarva Shiksha Abhiyan, East Champaran at Motihari).

It is needless to say that claim of the petitioner is to be considered by respondent no.8 in accordance with law by reasoned and speaking order and dues, if found admissible, be paid to the petitioner expeditiously and without undue delay and preferably within three months from the date of submission of claim of the petitioner supported by measurement book. Petitioner should submit his claim within four weeks from today.

Writ petition stands disposed of.

(Madhuresh Prasad, J) s.hassan/- U