Ashiyana Nagar Management Commitee v. The State Of Bihar
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.3679 of 2024 ====================================================== Ashiyana Nagar Management Commitee through its Secretary Mukesh Kumar (Male) aged about 44 Years, Son of Late Nageshwr Singh, Resident of 45, Phase-1, P.S.-Rajeev Nagar, District-Patna ... Petitioner
Versus
1.
The State of Bihar through its Principal Secretary Energy Department, 1st Floor, Vidyut Bhawan-II, Bailey Road, Patna.
2.
The Chairman, Bihar State Power Holding Corporation Limited. Vidyut Bhawan Bailey Road, Patna.-21, Bihar.
3.
The Managing Director, South Bihar Power Distribution Company Limited, Vidyut Bhawan, Bailey Road, Patna-21, Bihar.
4.
The Executive Engineer, Electric Supply Division, Ashiyana PESU (W), Patna, Bihar.
5.
The Assistant Electrical Engineer (Revenue), Electric Supply Division, Ashiyana PESU (W), Patna, Bihar. ... Respondents ====================================================== Appearance :
For the Petitioner :
Mr.Madhav Raj, Adv.
For the Company :
Mr.Kunal Tiwary, Adv.
====================================================== CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY ORAL ORDER 14-02-2025 Having regard to the fact that the petitioner is having an alternative and effective statutory remedy of approaching the Consumer Grievance Redressal Forum under Section 42(5) of the Electricity Act, 2003, this Court is not inclined to entertain the present Writ Petition.
2. Liberty is granted to the petitioner to approach the C.G.R.F. within a period of four weeks from today.
3. On such case being filed, the C.G.R.R. shall consider the same and decide the case within a period of four weeks and pass necessary orders in accordance with law.
4. With the above directions, the present Writ Petition
Patna High Court CWJC No.3679 of 2024(10) dt.14-02-2025 2/2 stands disposed of.
5. Pending final orders of the C.G.R.F., the authorities are directed not to disconnect the electricity supply to the petitioner provided the petitioner continued to pay the monthly charges of the electricity.
(A. Abhishek Reddy , J) Shamshad/- U