Chhotiya Construction Pvt. Ltd. v. The State Of Bihar
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.4956 of 2022 ====================================================== Chhotiya Construction Pvt. Ltd. having its Restered Office at East Gandhi Maidan, Jehanabad through its Managing Director, Ashok Kumar, aged about 60 years, Male, Son of Late Raj Nandan Singh @ Raj Nandan Sharma, Resident of East Gandhi Maidan, P.S.- Jehanabad, District- Jehanabad. ... ... Petitioner/s
Versus
1.
The State of Bihar through the Principal Secretary, Minor Irrigation Department, Government of Bihar, Patna.
2.
The Chief Secretary, Minor Irrigation Department, Government of Bihar, Patna.
3.
The Superintending Engineer, Minor Irrigation Circle, Gaya, District Gaya, Bihar.
4.
The Executive Engineer, Minor Irrigation Circle, Gaya, District Gaya, Bihar. 5.
M/s Maa Laxmi Construction, a Registered Partnership Firm having its place of business Village Kairwa, P.O. Sahobigha, P.S. Ghoshi, District Jehanabad through one of its Partner namely Ravish Kumar Sharma, Aged about 35 years, Male, son of Vinay Kumar Sharma, Resident of Village Kazi Fatehpur, P.O. Dadhma, P.S. Belaganj, District - Gaya. ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr. Prabhat Ranjan, Advocate For the State :
Mr. Santosh Chandra Bhaskar, AC to GP 11 ====================================================== CORAM: HONOURABLE THE CHIEF JUSTICE and HONOURABLE MR. JUSTICE PARTHA SARTHY ORAL ORDER (Per: HONOURABLE THE CHIEF JUSTICE) 24-01-2023 Petitioner has prayed for the following relief(s) :- "(i) Quashing of the decision of the Technical Bid Evaluation Committee dated 10.03.2021 (Annexure 2 Series) in connection with Notice Inviting Tender No. 09/2021-22 by which, the Technical Bid of the petitioner has been rejected in terms of Clause 4.8 of the SBD on the ground. that the firm stands debarred;
Patna High Court CWJC No.4956 of 2022(4) dt.24-01-2023 2/2 (ii) Direction upon the Respondent to open the Financial Bid of the petitioner and in case the Bid is technically and financially viable, a consequential direction to allot the work to the petitioner; and (ii) Restraining the Respondents from finalizing the Tender in connection with NIT No. 09/2021-22 and creating any third party rights during the pendency of the present writ petition."
Learned counsel for the petitioner seeks permission to withdraw the present petition.
Permission granted.
The instant petition stands disposed of as withdrawn. Needless to add with the withdrawal of the present petition, the interim order dated 13.5.2022 stands vacated. Interlocutory Application(s), if any, shall stand disposed of.
(Sanjay Karol, CJ) ( Partha Sarthy, J) Prakash/K.C Jha U