M/S Eclat Industries Ltd. v. The Bihar State Electricity Bo
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.9182 of 2010 ====================================================== M/S Eclat Industries Ltd. through its Managing Director Bashisth Narayan Choubey, S/O Late Dr. R.R. Choubey, Having Registered Office At C-30 And 31 Industrial Area, Patliputra,Patna-800013. .... .... Petitioner/s
Versus
1. The Bihar State Electricity Board, through its Secretary, Vidyut Bhawan, Bailey Road, Patna
2. The Chairman, Bihar State Electricity Board, Vidyut Bhawan, Bailey Road, Patna
3. The Secretary, Bihar State Electricity Board,Vidyut Bhawan, Bailey Road, Patna
4. The General Manager cum Chief Engineer, PESU, Patna.
5. The Electrical Superintending Engineer, Bihar State Electricity Board, PESU (West), Patna.
6. The Electrical Executive Engineer, Electric Supply Division,Patliputra Colony,Patna.
7. The Assistant Electrical Engineer, Electric Supply Division, Patliputra Colony,Patna.
.... .... Respondent/s ====================================================== Appearance :
For the Petitioner/s : Mr. Vivek Prasad Mr.Sanjay Kumar Olha For the Respondent/s : Mr. Prakash Kumar ====================================================== CORAM: HONOURABLE MR. JUSTICE BIRENDRA PRASAD VERMA ORAL ORDER 06-04-2015 Learned counsel appearing on behalf of the petitioner as also learned counsel appearing on behalf of the respondents are unanimous in their submissions that the valid grievances of the petitioner have already been redressed. Therefore, the present matter has become infructuous.
In above view of the matter, the writ petition stands dismissed as infructuous.
Arvind/- (Birendra Prasad Verma, J) U