IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.18674 of 2014 =========================================================== Bipin Bihari Singh Son of Shri Harischandra Singh, Resident of Village - Ami (Chauhani Patti), P.S. Dighwara, District- Saran (Chapra). .... .... Petitioner/s

Versus

1. The National Highway Authority of India through its Chairman, NHAI, New Delhi.

2. The Project Director, National Highway Authority of India, saran at Chapra.

3. The District Collector, Saran at Chapra District.

4. The District Land Acquisition Officer-cum-Competent Officer, NH-19, Project Saran, District- Chapra.

5. The Circle Officer, Dighwara, Saran.

.... .... Respondent/s =========================================================== Appearance :

For the Petitioner/s : Mr. Ram Kishore Singh, Adv. For the Respondent/s : Mr. Sita Ram Yadav, GP16 For the NHAI : Mr. S.N. Pathak, S.C. (NHAI) =========================================================== CORAM: HONOURABLE MR. JUSTICE SHIVAJI PANDEY ORAL JUDGMENT Date: 12-09-2017 Heard learned counsel for the parties.

Learned counsel for the petitioner submits that the land of the petitioner has been acquired under the National Highway Act for construction of national highway. He further submits that the Circle Officer of the area concerned has held an enquiry and determined the nature of the land and verified the right, title and possession of the petitioner inclusive the area under acquisition. He has further submitted that the award has been prepared but, no payment has been made to the petitioner as yet. Learned counsel for the State submits that the award is

Patna High Court CWJC No.18674 of 2014 dt.12-09-2017 ready and the payment will be made to the petitioner expeditiously. Let the competent authority should release the amount of compensation to the petitioner if the compensation amount has been arrived after proper enquiry under the National Highway Act and the same should be paid to the petitioner within a period of eight weeks from the date of receipt/production of a copy of this order. With the aforementioned observation and direction, this application is disposed of.

(Shivaji Pandey, J) Rishi/- AFR/NAFR NAFR CAV DATE NA Uploading Date 14.09.2017 Transmission Date NA