← Library
Patna High CourtCWJC/10919/2021disposed

Kanak Lata Devi v. The State Of Bihar

2022-02-18Mr. Justice Mohit Kumar Shah,Mr. Justice Rajan Gupta2 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.10919 of 2021 ====================================================== 1.

Kanak Lata Devi W/o Deepak Kumar Singh Resident of Adarsh Nagar, Amarpur Road, Babutola, P.S. Banka, District- Banka. 2.

Subodh Jha Son of Late Jagannath Jha Resident of Ward No.15, Azad Chowk, Babu Tola, Police Station- Banka, District- Banka. 3.

Anjani Kumar Son of Late Shashank Shekhar Das Resident of Ward No. 16, Naya Tola, Police Station- Banka, District- Banka. ... ... Petitioner/s

Versus

1.

The State of Bihar 2.

The Principal Secretary, Department of Building Construction, Government of Bihar, Patna.

3.

The Principal Secretary, Department of Finance, Government of Bihar, Patna.

4.

The Engineer-in-Chief, Building Construction Department, Government of Bihar, Patna.

5.

The Chief Engineer, Building Construction Department, Patna. 6.

The Superintending Engineer, Building Construction Circle, Bhagalpur. 7.

The Executive Engineer, Building Construction Division, Banka. 8.

The Assistant Engineer, Building Construction Division, Banka. ... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr.Rajib Ranjan Jha, Advocate For the Respondent/s :

Mr.Lalit Kishore ( AG ) ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJAN GUPTA and HONOURABLE MR. JUSTICE MOHIT KUMAR SHAH ORAL ORDER (Per: HONOURABLE MR. JUSTICE RAJAN GUPTA) 18-02-2022 The learned counsel for the petitioners submits that they have not been paid the admitted dues for the work executed by them. As per averments made in paragraph no. 1, they have completed the entire work as per the agreement. In view of the aforesaid statement, we dispose off the

Patna High Court CWJC No.10919 of 2021(2) dt.18-02-2022 2/2 writ petition with the observation that in case the petitioners file a representation before the Executive Engineer, Building Construction Division, Banka, respondent no. 7 herein, within two weeks, he will take a decision thereon within two weeks thereafter. In case any amount is found payable, it shall be released forthwith.

(Rajan Gupta, J) (Mohit Kumar Shah, J) S.Sb/- U