Rajendra Ray v. The State Of Bihar Through The Secretary,
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.11192 of 2021 ====================================================== Rajendra Ray, son of Shri Mahadev Ray, resident of village Narayanpur, P.O. - Bhatha Sonaho, P.S. - Parsa Saran, District- Saran, Bihar, PIN Code841460. ... ... Petitioner/s
Versus
1.
The State of Bihar through the Secretary, Rural Works Department, Government of Bihar, Patna.
2.
The Secretary, Rural Works Department, Government of Bihar. 3.
The Deputy Secretary, Rural Works Department, Government of Bihar, Patna.
4.
The Additional Chief Secretary, Road Construction Department, Government of Bihar, Patna.
5.
The Engineer-in-Chief, Rural Works Department, Government of Bihar, Patna.
6.
The Chief Engineer-03, Rural Works Department, Bihar, Patna. 7.
The Superintending Engineer, Rural Works Department, Works Circle, Chapra.
8.
The Executive Engineer, Rural Works Department, Works Division, Madhaura, Chapra.
9.
The Executive Engineer, Road Construction Department, Road Division, Chapra.
... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr. Shambhu Nath, Advocate For the Respondent/s :
Mr. Amit Prakash, GA-13 ====================================================== CORAM: HONOURABLE THE CHIEF JUSTICE and HONOURABLE MR. JUSTICE S. KUMAR ORAL JUDGMENT (Per: HONOURABLE THE CHIEF JUSTICE) Date : 21-09-2021 Petitioner has prayed for the following relief(s):- " That the present writ application is being preferred on behalf of the petitioner invoking the writ jurisdiction of this Hon'ble Court for seeking direction to the Executive Engineer, Rural Works Department, Works Division, Madhaura, Chapra, respondent no.8, to transfer rest 5 Km, out of 26 Km, of Bheldi-Bhitthi Bazar Road to the Road Construction Department,
Patna High Court CWJC No.11192 of 2021 dt.21-09-2021 2/2 Government of Bihar in compliance of decision of State Government, as contained in notification no. 6264 dated 20.05.2016, Annexure P-1."
From the response filed by the State, it is apparent that the land with respect to 26 Kilometers stretch of road stands handed over the Road Construction Department, Government of Bihar. It is further pointed out that 5 Kilometers stretch of road remains to be constructed.
Thus, in our considered view the present petition has become infructuous.
Accordingly, the present petition stands disposed of with a direction to the respondent authorities to complete the road expeditiously in accordance with law and also granting liberty to the petitioner to approach the authority, if so required and desired in accordance with law.
Interlocutory Application(s), if any, shall also stands disposed of.