Hareshwar Prasad Singh v. The Chief General Manager-Cum-Regional Manager
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.7143 of 2026 ====================================================== Hareshwar Prasad Singh Son of Late Jaglal Singh @ Jaglal Rai, Resident of Village- Chaknoor, P.S.- Dighwara, District- Saran. ... ... Petitioner/s
Versus
1.
The Chief General Manager-cum-Regional Manager National High Authority of India, Patna.
2.
The Project Director, National Highway Authority, Sherpur, Dighwara Ring Road, Chapra, Saran, Bihar.
3.
The State of Bihar, through the Principal Secretary, Road Construction Department, Govt. of Bihar, Patna.
4.
The Principal Secretary, Department of Revenue and Land Reforms, Govt. of Bihar, Patna 6.
5.
The Director, Land Acquisition, Department of Revenue and Land Reforms, Bihar, Patna.
6.
The District Magistrate, Saran.
7.
The Competent Officer-cum-District Land Acquisition Officer, Saran. 8.
Arbitrator-cum-Divisional Commissioner, Saran at Chapra ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr. Dhananjay Mishra, Advocate Mr. Nilesh Kumar Nirala, Advocate Mr. Arun Kumar, Advocate For the State :
Mr. Standing Counsel (13), J.K. Roy For the NHAI :
Dr. Maurya Vijay, Advocate Mr. Gaurav Govinda, Advocate ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJIV ROY ORAL ORDER 06-07-2026 Learned counsel for the petitioner prays for and is allowed to implead the Arbitrator-cum-Divisional Commissioner, Saran at Chapra as respondent no. 8 in course of the day.
2. Heard the parties.
3. The present petition has been preferred for the following relief(s):
" (i) For issuance of order/s, directions/s,
Patna High Court CWJC No.7143 of 2026(3) dt.06-07-2026 2/2 command/s or including writ in the nature of mandamus to direct the concerned respondent authorities to re-determination on award which is provided under Section 28A of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and enhance the compensation amount as per revised rate as ascertained by the Government. (ii) For any other relief/s for which the petitioner may found entitled in the facts and circumstances of the present case."
4. After some argument, learned counsel for the petitioner submits that he shall be approaching the Arbitrator-cumDivisional Commissioner, Saran at Chapra for the redressal of the grievance.
5. Learned State counsel has no objection to it.
6. In that background, granting liberty, the writ petition stands disposed of.
(Rajiv Roy, J) Adnan/- U