Madan Choudhary v. The State Of Bihar And ORS
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.1581 of 2016 ====================================================== Madan Choudhary, Son of Sri Satyadev Choudhary, Resident of villageGamharia, P.O.- Sirsia Kala, P.S.- Bhargama, District- Araria ... ... Petitioner/s
Versus
1.
The State of Bihar through the Principal Secretary Public Health Engineering Department, Govt. of Bihar, Patna 2.
The Principal Secretary, Public Health Engineering Department, Govt. of Bihar, Patna 3.
The Engineer-in-Chief-cum-Special Secretary, Public Health Engineering Department, Govt. of Bihar, Patna 4.
The Chief Engineer, Department of Public Health Engineering Mechanical, Govt. of Bihar, Patna 5.
The Zonal Chief Engineers, Purnea Zone, Purnea 6.
The Superintending Engineer, Public Health Engineering Circle- Purnea 7.
The Executive Engineer, Public Health Division, Araria 8.
The Sub-Divisional Officer-cum-Assistant Engineer, Public Health Engineering, Sub-Division, Araria 9.
The District Magistrate, Araria 10.
The District Provident Fund Officer, Araria 11.
The Treasury Officer, Araria 12.
The Accountant General A and E, Bihar, Patna ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr. Siyaram Pandey, Advocate For the Respondent/s :
Mr. AAG-15 For the Accountant :
Mr. Binod Kumar Labh, Advocate General ====================================================== CORAM: HONOURABLE MR. JUSTICE PRABHAT KUMAR SINGH ORAL ORDER 09-02-2023 It is submitted on behalf of the petitioner that during pendency of the writ petition grievance of the petitioner has already been redressed. However, till date the arrears of promotion as well as arrears of salary of the period has not been paid to him.
Patna High Court CWJC No.1581 of 2016(7) dt.09-02-2023 2/2 Considering the nature of grievance, writ petition is disposed of with a direction of the petitioner to file a detailed representation before the Engineer-in-Chief-cum-Special Secretary, Public Health Engineering Department, Govt. of Bihar, Patna (respondent No. 3).
If such representation is filed within a period of four weeks from today, the same shall be disposed of, in accordance with law, by reasoned and speaking order within a period of three months from the date of receipt/production of copy of this order.
It goes without saying that if claim of the petitioner finds favour, the entire payment should be made within a period of six months thereafter.
(Prabhat Kumar Singh, J) Navya/- U