← Library
Patna High CourtCWJC/10432/2026disposed

Ramavati Devi v. The Managing Director, National Highway Authority Of India

2026-07-21Mr. Justice Alok Kumar2 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.10432 of 2026 ====================================================== 1.

Ramavati Devi Wife of Vijay Kumar Prajapati @ Vijay Kumar Bharti, R/o village Badgaon- Kala P.S. Adhoura, District Kaimur at Bhabua. 2.

Badaruddin Ansari, S/o Kamal Miya, R/o village Marpa, P.S. Adhoura, District Kaimur at Bhabua.

3.

Jitendra Ram, S/o late Ram Naresh Ram, R/o village Barwan- Kala, P.S. Adhoura, District Kaimur at Bhabua.

... ... Petitioner/s

Versus

1.

The Managing Director, National Highway Authority of India New Delhi. 2.

The State of Bihar through the District Magistrate cum Collector, Kaimur at Bhabua 3.

Additional Collector, Kaimur at Bhabua.

4.

The Deputy Collector of Land Reforms Officer cum Competent Authority, Kaimur at Bhabua.

5.

Competent Authority cum Land Acquisition Officer, Kaimur at Bhabua. 6.

Anchaladhikari, Block Bhabua, Kaimur at Bhabua. 7.

The Project Director, NHAI, PIU SASARAM.

... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr.Tribhuwan Narayan, Advocate For the NHAI :

Mr.Rajesh Kumar Shandliya, Advocate Ms.Ankita Kumari, Advocate For the Respondent/s :

Mr.Rakesh Prabhat, AC to SC-21 ====================================================== CORAM: HONOURABLE MR. JUSTICE ALOK KUMAR ORAL ORDER 21-07-2026 Heard learned counsel for the petitioners and learned counsel for the State.

2. In the instant writ petition, the petitioners have prayed for the following reliefs:- "1. That this present writ application is being filed for issuance of writ in nature of mandamus or any appropriate writ to direct the respondent authorities to consider the applications filed by the petitioners respectively, to pay the

Patna High Court CWJC No.10432 of 2026(2) dt.21-07-2026 2/2 compensation of their dwelling houses which has been constructed in Khata No. 317 plot No. 1597 situated at Mauza Sio, Thana No. 443 Anchal Bhabua, District Kaimur at Bhabua, and being acquired to construct the Bharat Mala Project phage-II (Lot-9, Package-3) Varanasi - Ranchi - Kolkata Express Way. Though the compensation amount of their land has been fixed to the rate of Domicile but no compensation amount has been assessed/paid for their dwelling houses which are going to be demolished."

3. At the outset, learned counsel for the petitioners seeks permission to withdraw the present Writ petition in order to pursue his remedy before the appropriate authority.

4. In view of the above, the present Writ petition is disposed of with the direction to the Authority concerned to decide the issue of the petitioner within a period of three months from the date of filing of the representation/Appeal by the petitioner.

(Alok Kumar, J) manish/- U