IN THE HIGH COURT OF JUDICATURE AT PATNA

Miscellaneous Jurisdiction Case No.3100 of 2015 In Civil Writ Jurisdiction Case No. 7682 of 2015 ======================================================

1. The Bihar State Power Generation Company Ltd. through its Managing Director Vidyut Bhawan, Bailey Road, Patna.

2. The Managing Director, Bihar State Power General Company Limited, Vidyut Bhawan, Bailey Road, Patna. null null

3. The Chief Engineer (P & D) Bihar State Power Generation Company Limited Vidyut Bhawan, Bailey Road, Patna.

4. The General Manager-cum-Chief Engineer, Bihar State Power Generation Company Limited, Barauni thermal Power Station. .... .... Petitioners

Versus

1. McNally Bharat Engineering Company Ltd. having its Registered Office at 2, Mangoe Lane, Kolkata- 700001, and corporate Office at Eco Space Campus- 2B, premises No. 11 F/12, new Town, Rajarhat, Kolkata- 700156. .... .... Opposite Parties ====================================================== Appearance :

For the Petitioners : Mr. Vinay Kirti Singh, Advocate ====================================================== CORAM: HONOURABLE DR. JUSTICE RAVI RANJAN ORAL ORDER 09-03-2016 It is submitted on behalf of the Bihar State Power Generation Company Ltd. that this application has become infructuous as the award in the concerned matter has already been made and pronounced.

Accordingly, this application is dismissed as infructuous. (Dr. Ravi Ranjan, J) SC/- U