M/S P.K. Construction Pvt. v. The State Of Bihar Through The Chief Secretary,
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.16513 of 2021 ====================================================== M/s P.K. Construction Pvt. Through its Proprietor Pintu Kumar, Male, Aged about 41 years, son of Ranjit Mahto, Resident of Khandpar, Sheikhpura, District- Sheikhpura.
... ... Petitioner/s
Versus
1.
The State of Bihar through the Chief Secretary, Government of Bihar, Patna. 2.
The Minor Water Resource Department through its Principal Secretary, Government of Bihar, Patna.
3.
The Principal Secretary, Minor Water Resource Department, Government of Bihar, Patna.
4.
The Superintending Engineer, Minor Water Resource Circle, Munger. 5.
The Chief Engineer, Minor Water Resource Circle, Munger. 6.
The Executive Engineer, Minor Irrigation Division, Sheikhpura. ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr.Kunal Tiwary, Adv.
For the Respondent/s :
Mr. Santosh Chandra Bhaskar, AC to GP-11 ====================================================== CORAM: HONOURABLE MR. JUSTICE RAJAN GUPTA and HONOURABLE MR. JUSTICE MOHIT KUMAR SHAH ORAL ORDER (Per: HONOURABLE MR. JUSTICE RAJAN GUPTA) 11-04-2022 The petitioner seeks a direction to the Respondent authorities in particularly the Chief Engineer, Minor Resources Department, Bhagalpur for accepting the recommendation of Superintending Engineer, Minor Irrigation Circle, Munger dated 3rd August, 2021, whereby and where under the Superintending Engineer has made recommendation before the Chief Engineer for extending the time period allotted to the petitioner for completing the work.
Patna High Court CWJC No.16513 of 2021(3) dt.11-04-2022 2/2 The main plea of the petitioner is that it has completed 85% of the work and as far as rest of the work is concerned, it is ready to complete the same within ten days. The committee has already accepted its proposal but still no response is forthcoming.
Under the circumstances, we dispose of the present writ petition with a direction that in case the petitioner approaches the Respondent No. 2 with a fresh representation within ten days from today, he shall consider the same and pass appropriate orders within ten days thereof.
(Rajan Gupta, J) ( Mohit Kumar Shah, J) Tiwary/- U