Patna High Court CWJC No.4118 of 2013 (5) dt.19-01-2016

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.4118 of 2013 ======================================================

1. Lal Mohan Paswan Son Of Late Chulhai Paswan Resident Of Village, P.O. Susta, P.S. Sadar, Distt.- Muzaffarpur .... .... Petitioner/s

Versus

1. The State Of Bihar

2. The Commissioner-Cum-Principal Secretary, Water Resources And Development, Government Of Bihar, Patna

3. The Engineer-In-Chief-Cum-Special Secretary, Water Resources And Development Department, Govt. Of Bihar, Patna

4. The Chief Engineer, Water Resources, Anishabad, Patna

5. The Chief Engineer, Water Resources, Muzaffarpur

6. The Superintending Engineer, Water Ways Circle, Muzaffarpur

7. The Executive Engineer, Drainage And Investigation Division, Ratwara, Muzaffarpur

8. The Sub-Divisional Officer, Drainage And Investigation Sub-Division, Sahpur Patori, Samastipur .... .... Respondent/s ====================================================== Appearance :

For the Petitioner/s : Mr. Pravin Kumar Sinha, Advocate For the Respondent/s : Mr. Gautam Bose,AAG8 Mr. Rohit Mishra, ====================================================== CORAM: HONOURABLE MR. JUSTICE SHIVAJI PANDEY ORAL ORDER 19-01-2016 Heard learned counsel for the petitioner and learned counsel for the State.

In the present case, the petitioner is seeking relief for regularisation of his service working with the Executive Engineer, Drainage and Investigation Division, Ratwara, Muzaffarpur.

Learned counsel for the petitioner submits that petitioner is a Sweeper discharging the duty part-time regularly. He has been paid wages regularly and submits that

Patna High Court CWJC No.4118 of 2013 (5) dt.19-01-2016 his case should be considered for regularisation. Learned counsel for the State submits that petitioner is a part-time Sweeper attached with the Executive Engineer must be working for livelihood elsewhere.

Be that as it may, the petitioner may file a detailed representation to the authority concerned raising his grievance and authority will pass an appropriate order in accordance with law within a period of three months from the date of receipt/production a of a coy of this order.

With the aforesaid observation this writ petition is disposed of.

(Shivaji Pandey, J) Vinay/- U