Shyama Devi v. The State Of Bihar
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.11112 of 2024 ====================================================== Shyama Devi, Wife of Late Shashi Bhushan Prasad, Resident of villageLohrajpur, P.O.- Katauna, P.S.- Giriyak, Distt.- Nalanda at present- mohallaPatel Nagar, P.S.- Nawada (Town), District- Nawada. ... ... Petitioner/s
Versus
1.
The State of Bihar through Principal Secretary, Bhawan Nirman Vibhag. 2.
The Deputy Secretary, Govt. of Bihar, Patna (Bihar). 3.
The Chief Engineer cum Special Secretary, Bhawan Nirman Vibhag, Patna (Bihar).
4.
The Superintending Engineer, Bhawan Nirman Vibhag, Gaya (Bihar). 5.
The Executive Engineer, Bhawan Nirman Vibhag, Nawada (Bihar). ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s :
Mr. Rajeev Nayan, Advocate For the Respondent/s :
Mr. Ajay Behari Sinha, GA- 8 ====================================================== CORAM: HONOURABLE MR. JUSTICE HARISH KUMAR ORAL JUDGMENT Date : 23-04-2025 Heard the parties.
2. A copy of the counter affidavit has been served upon the learned Advocate for the petitioner, just in a while.
3. Learned Advocate for the petitioner referring to the averments made in the counter affidavit has thus submitted that despite the fact that the calculation has been made and an amount of Rs.7,03,277/- is found admissible under the head of GPF and GIS, but till date the same has not been paid.
4. It is categorically averred in the counter affidavit that on the basis of the calculation, the headquarter vide its letter
Patna High Court CWJC No.11112 of 2024 dt.23-04-2025 2/2 no. 2361 (anu) dated 05.10.2024 requested the concerned respondents to provide an allotment of Rs.7,03,277/- so that the admissible amount may be paid. The copy of the letter has been placed on record as Annexure- B to the counter affidavit.
5. Considering the averments made in the counter affidavit, this Court deems it appropriate to dispose of the writ petition with a direction to the concerned respondents, including Executive Engineer, Building Construction Department, Nawada to ensure payment of aforenoted admissible amount preferably within a period of twelve weeks from today.
6. In case of any delay in extending the payment of admissible amount, which is due since 31.01.2020, the petitioner shall be entitled to interest at the rate of 6% per annum over the delayed payment, which shall be realized from the erring officials.
7. The writ petition stands disposed of.
(Harish Kumar, J) uday/- AFR/NAFR NAFR CAV DATE NA Uploading Date 25.04.2025 Transmission Date NA