IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.4005 of 2021 ====================================================== Krishna Nandan Singh S/o- Late Beni Singh Village- Rudasi Gagari Gagari, P.S. and Block- Shekhpura, District- Shekhpura. ... ... Petitioner/s

Versus

1.

The State of Bihar through the Chief Secretary Government of Bihar, Patna. 2.

The Director Land Conversation Bihar, Patna.

3.

The Principal Secretary Agriculture Department Government of Bihar, Patna.

4.

The Deputy District and Conservation, South Bihar, Patna. 5.

The Divisional Commissioner, Munger Division, Bihar. 6.

The District Magistrate, Shekhpura, Bihar.

7.

The Deputy Collector Land Reforms, Shekhpura, Bihar. 8.

The Circle Officer, Chevara, District- Shekhpura. 9.

The Block Development Officer, Chevara, District- Shekhpura. 10.

The Sub- Division Officer, Shekhpura. The Surebdar Pandit, S/o Sri Bhuneshar Pandit, Village- Bajnathpur Lutaut, P.O.- Chhatiyara, P.S.- Karand, Block- Chawara, District- Shekhpura.

11.

The Superintendent of Police, Shekhpura.

12.

The Deputy Superintendent of Police, Shekhpura. 13.

The Station House Officer, P.S.- Karandoy, District- Shekhpura. 14.

Assistant Director Land Conservation Shekhpura. ... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr.Pushpendra Priyedarshi, Adv.

For the Respondent/s :

Mr.Dhurjati Kumar Prasad, GP-14 ====================================================== CORAM: HONOURABLE MR. JUSTICE MOHIT KUMAR SHAH ORAL ORDER 18-12-2024

1. Though the present writ petition has been filed for directing the respondents not to construct check dam on River Kharach, however, at the outset, the learned counsel for the respondent-State has submitted by referring to paragraph no.7 of the counter affidavit filed in the present case that on account of

Patna High Court CWJC No.4005 of 2021(4) dt.18-12-2024 2/2 the protest made by the villagers of Kapasi Village, the construction work of pucca check dam has been stopped, hence the present writ petition has been rendered infructuous.

2. Accordingly, the present writ petition stands disposed off, however, with liberty to the petitioner to take recourse to the due process of law, in case the construction work of the check dam is resumed.

(Mohit Kumar Shah, J) sonal/- U