← Library
Patna High CourtCWJC/12563/2014disposed

The General Manager Cum Chief Engineer And ORS v. The Bihar Electricity Regulatory Commission And ORS

2016-02-19Mr. Justice Rakesh Kumar1 pages

IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No. 12563 of 2014 ======================================================

1. The General Manager cum Chief Engineer Muzaffarpur, Electric Supply Area, Muzaffarpur.

2. The Electrical Superintending Engineer Muzaffarpur Electrical circle.

3. The Electrical Executive Engineer Muzaffarpur (West) Electric Supply Division Muzaffarpur.

4. The Electrical Executive Engineer (C & R) Electrical Supply Circle, Muzaffarpur.

.... .... Petitioners

Versus

1. The Bihar Electricity Regulatory Commission through its Secretary, Vidyut Bhawan II, Bailey Road, Patna.

2. The Electricity Ombudsman Vidyut Bhawan- II, Bailey Road, Patna.

3. The Consumer Grievance Redressal Forum, Muzaffarpur.

4. M/s Ambika Bhawani Cold Storage Pvt Ltd., Bakhara, Saraiya, Muzaffarpur.

.... .... Respondents ====================================================== Appearance :

For the Petitioner/s : Mr. Vinay Kirti Singh For the Respondent/s : Mr. Suraj Samdarshi ====================================================== CORAM: HONOURABLE MR. JUSTICE RAKESH KUMAR ORAL ORDER 2.

19-02-2016 In view of changed circumstances, Sri Vinay Kirti Singh, learned counsel for petitioners, in presence of Sri Suraj Samdarshi, learned counsel for the respondent no. 4, makes a prayer for disposal of the present writ petition so that the petitioner may avail appropriate remedy.

The prayer is allowed.

The writ petition stands disposed of.

(Rakesh Kumar, J.) Anay U