Patna High CourtREQ. CASE/20/2015withdrawn

Nevilal Rohita Constractors Pvt. Ltd. v. The East Central Railway Through The General Manager East Central Railway And ORS

2016-08-19Mr. Justice Vikash Jain1 pages

Patna High Court REQ. CASE No.20 of 2015 (11) dt.19-08-2016

IN THE HIGH COURT OF JUDICATURE AT PATNA

Request Case No.20 of 2015 ====================================================== Nevilal Rohita Contractors Pvt. Ltd. through its Managing Director Nevilal Rohita, son of late Ram Kishun Rohita, resident of Mohalla+ Police Station- Birpur, District- Supaul.

.... .... Petitioner

Versus

1. The East Central Railway through the General Manager East Central Railway, Hajipur, district- Vaishali.

2. The Chief Administrative Officer Construction) East Central Railway, Mahendrughat, Patna.

3. The Deputy Chief Engineer (Construction), II, East Central Railway, Hajipur, District- Vaishali.

4. The Executive Engineer (Construction), II, East Central Railway, Hajipur, District- Vaishali (Hajipur to Sugauli New B.G. Line Project, Hajipur).

.... .... Respondents ====================================================== Appearance:

For the Petitioner : Mr. Nand Kishore Singh, Adv. Mr. Basant Kumar Singh, Adv.

For the Respondents : Mr. D.K. Sinha, Sr. Adv. Mr. Bijay Kumar Sinha, Adv.

====================================================== CORAM: HONOURABLE MR. JUSTICE VIKASH JAIN ORAL ORDER 11 19-08-2016 After some arguments, learned counsel for the petitioner seeks permission to withdraw the present request case with liberty to approach the respondents with a fresh demand for arbitration in accordance with law.

2. Permission is accorded. The application is dismissed as withdrawn with the aforesaid liberty.

(Vikash Jain, J) Md. Ibrarul/Chandran U