M/S Indra Narain Singh Contractors Pvt. Ltd. v. The State Of Bihar And ORS
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.2401 of 2018 ====================================================== M/s Indra Narain Singh Contractors Pvt. Ltd., 76, Vidhayak Colony, Kautilya Nagar, Patna- 800014, represented through its Managing Director, Mr. Manoj Kumar Singh, son of Mr. Indra Narain Singh. .... .... Petitioner/s
Versus
1. The State of Bihar through Principal Secretary, Building Construction Department, Bihar, Patna.
2. The Engineer-in-Chief cum Additional Commissioner cum Special Secretary, Building Construction Department, Bihar, Patna.
3. Chief Engineer (North), Building Construction Department, Bihar, Patna.
4. Technical Secretary to the Engineer-in-Chief, Building Construction Department, Bihar, Patna.
5. Departmental Tender Committee through Principal Secretary, Building Construction Department, Bihar, Patna.
.... .... Respondent/s ====================================================== Appearance:
For the Petitioner/s : Mr. Aditya Prakash Sahay For the Respondent/s : Mr. Chitranjan Sinha, PAAG-2 ====================================================== CORAM: HONOURABLE MR. JUSTICE MOHIT KUMAR SHAH ORAL ORDER 06-09-2018 The learned counsel for the petitioner submits that the petitioner has filed a representation dated 14.09.2017 before the Secretary, Building Construction Department, Government of Bihar, Patna against the order dated 05.09.2017 passed by the Engineer-in-Chief, Building Construction Department, Government of Bihar, Patna, hence the same be directed to disposed off within a stipulated time frame.
In view of the aforesaid, the writ petition is disposed off as withdrawn with direction to the Secretary, Building
Patna High Court CWJC No.2401 of 2018 (5) dt.06-09-2018 2/2 Construction Department, Government of Bihar, Patna to dispose of the representation of the petitioner by a reasoned and speaking order within a period of six weeks from today. (Mohit Kumar Shah, J) S.Sb/- U