IN THE HIGH COURT OF JUDICATURE AT PATNA

Civil Writ Jurisdiction Case No.663 of 2024 ====================================================== Renu Devi Wife of Ram Subhag Singh Resident of Road no.15E, Rajeev Nagar, Police Station-Rajeev Nagar, Patna at present resident of Vasant Vihar Colony, Ward No. 02 Ghurdaur Road, Uttari Nepali Nagar PS Rajeev Nagar Patna.

... ... Petitioner/s

Versus

1.

The Bihar State Power Holding Company Limited through its Chairman, Vidyut Bhawan, Baily Road, Patna.

2.

The South Bihar Power Distribution Company Limited through its Managing Director, Vidyut Bhawan, Bailey Road, Patna. 3.

The General Manager-cum-Chief Engineer, Patna Electric Supply Union, South Bihar Power Distribution Company Limited, Baily Road, Patna. 4.

The Executive Engineer, Electric Supply Division, South Bihar Power Distribution Company Limited, Danapur, Patna. 5.

The Assistant Electric Engineer, Electric Supply Sub Division, South Bihar Power Distribution Company Limited, Digha, Patna. ... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s :

Mr. Gyan Prakash For the Respondent/s :

Mr. Vinay Kirti Singh ====================================================== CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY ORAL ORDER 31-01-2024 The prayer sought for in the present writ petition is to direct the Respondent No. 5 to accept the application of the petitioner for an electrical connection along with the requisite amount.

2. Learned counsel appearing on behalf of the respondents has stated that the writ petition may be disposed off with a direction to the Respondent No. 5 to accept the application made by the petitioner along with the requisite amounts and consider the same in accordance with law.

Patna High Court CWJC No.663 of 2024(2) dt.31-01-2024 2/2

3. Having regard to the above made submissions, the present writ petition is disposed off with a direction to the Respondent No. 5 to accept the application of the petitioner for an electrical connection along with the requisite amount and consider the same strictly in accordance with law. The Respondent No. 5 is directed to consider the said application within a period of four weeks from the date of the copy of the receipt of this order.

4. With the above direction, the present writ petition stands disposed off to the extent indicated above. (A. Abhishek Reddy, J) Ayush/- U