M/S. Sai Construction (Partnership Firm) v. Municipal Corporation Bilaspur
-1NAFR HIGH COURT OF CHHATTISGARH, BILASPUR WPC No. 2052 of 2020
1. M/s. Sai Construction (Partnership Firm) Having Office At Green Park Colony, Jarhabhata, Bilaspur, Through Its Partner Atul Shukla, S/o Shri Sudama Prasad Shukla, Aged About 47 Years, R/o Green Park Colony, Jarhabhata, Bilaspur Tehsil, District : Bilaspur, Chhattisgarh ---- Petitioner
Versus
1. Municipal Corporation Bilaspur Through Its Commissioner, Having Office At Vikas Bhawan, Nehru Chowk, Bilaspur, District : Bilaspur, Chhattisgarh
2. The Executive Engineer, Municipal Corporation Bilaspur, Having Office At Vikas Bhawan, Nehru Chowk, Bilaspur, District : Bilaspur, Chhattisgarh ------ Respondents For Petitioner :
Mr. Shishir Dixit, Advocate.
For State :
Mr. Mateen Siddiqui, Dy. Advocate Gen.
Hon'ble Shri Justice P. Sam Koshy Order on Board 22.09.2020
1. The present writ petition seems to be the non-processing of the claims put-forth by the petitioner to the respondents in-respect-of certain construction which was carried out by him.
2. The counsel for the respondents submits that perhaps from the pleadings available with the petition, there does not seem to be noncompletion certificate of the work provided to the petitioner, without which processing of the bills cannot be done.
3. Be that as it may, as the grievance of the petitioner arises out of a contractual obligation between the petitioner and the respondents
-2ends of justice would meet, if the petitioner is directed to approach the Respondent No. 1 for redressal of his grievance in-respect-of the non-settlement of his claims in-accordance with the agreement that was entered into between the parties.
4. Reserving the right of the parties to avail appropriate remedies as provided in the agreement/contract, the present writ petition stands disposed off.
Sd/- (P. Sam Koshy) Judge Rahul