Smt. Saraswati Soni v. State Of Chhattisgarh
NAFR HIGH COURT OF CHHATTISGARH, BILASPUR WPC No. 1244 of 2017 Smt. Saraswati Soni, W/o Shri Ghanshyam Soni, R/o MIC 162, Kabir Nagar, Raipur, Tah. And Distt. - Raipur (CG) ---- Petitioner
Versus
1. State Of Chhattisgarh Through Secretary, Department Of Urban Administration, Mantralaya, Naya Raipur, Distt. Raipur Chhattisgarh.
2. The Collector, District Raipur, Chhattisgarh
3. Sub Divisional Officer ( R), District Raipur, Chhattisgarh
4. Municipal Corporation, Raipur, Through Its Commissioner, Distt. Raipur (Chhattisgarh)
5. Zone Commissioner, Municipal Corporation, Raipur, Zone Office No. 8 Mohaba Bazar Raipur (Chhattisgarh) ---- Respondents Shri Parag Kotecha, counsel for the petitioner/s. Shri Dhiraj Wankhede, Govt. Advocate for the State. Shri Satish Gupta, counsel for the Corporation. Hon'ble Shri Justice Manindra Mohan Shrivastava Order On Board 05/05/2017 Heard.
This petition has been filed by the petitioner aggrieved by notice dated 26/04/2017 by which, the petitioner has been asked by the Corporation to remove construction made without grant of permission. Learned counsel for the petitioner submits that though the petitioner is possessed of building permission, the same could not be submitted before the authorities. The petitioner has placed on record a map. In the interest of justice, the petitioner is granted 15 days' time to submit
the building permission, if any with her, to the Zone Commissioner, Municipal Corporation, Raipur. Thereafter, depending upon the production of documents before the authority, appropriate steps may be taken by the authorities in accordance with law.
For a period of 15 days from the date of receipt of copy of this order, demolition shall not take place.
5.
With the said observations, this petition is finally disposed off. Sd/- (Manindra Mohan Shrivastava) Judge Deepti