$~O-41 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 19/2025 DSC ENGINEERING PVT. LTD.
.....Petitioner Through:
Mr. Vineet Tayal and Ms. Nishtha Wadhwa, Advs.
versus M/S LOMASH SLURRYTECH PVT. LTD.
.....Respondent Through:
Mr. Vijay Mishra, Adv.
CORAM:
HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
O R D E R
% 10.01.2025 I.A. 412/2025 (EXEMPTION) 1.
Exemptions allowed, subject to all just exceptions. 2.
The application stands disposed of.
O.M.P.(MISC.)(COMM.) 19/2025 3.
Heard.
4.
Issue notice.
5.
Learned counsel for the respondent accepts notice. 6.
Learned counsel for the respondent, on instructions, submits that he does not have any objection in extending the time period for making the arbitral award. However, according to him, the period may be extended only to the extent of 6 months from 07.01.2025. 7.
Learned counsel for the petitioner, however, submits that there are some applications pending before the Arbitral Tribunal and taking into The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 24/01/2025 at 12:58:23
consideration the number of witnesses to be examined, the matter perhaps may not be concluded within a period of 6 months, and, therefore, in the interest of justice, the aforesaid period may be extended to 12 months. 8.
Having heard the submissions made by the learned counsel appearing on behalf of the parties and in view of the controversy involved in the instant case, the Court deems it appropriate to extend the aforesaid period for rendering the arbitral award for 9 months, with effect from 07.01.2025. 9.
With the aforesaid, the instant petition stands disposed of. PURUSHAINDRA KUMAR KAURAV, J JANUARY 10, 2025 aks/sp The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 24/01/2025 at 12:58:23