← Library
High Court of DelhiO.M.P.(MISC.)(COMM.)/33/2024

Brilltech Engineers Private Limited v. Paarth Infrabuild Private Limited

2024-01-16Hon'Ble Ms. Justice Prathiba M. Singh1 pages

$~53 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P.(MISC.)(COMM.) 33/2024 & I.A. 1108/2024 BRILLTECH ENGINEERS PRIVATE LIMITED ..... Petitioner Through:

Mr. Ankur Singhal, Adv.

versus PAARTH INFRABUILD PRIVATE LIMITED ..... Respondent Through:

None.

CORAM:

JUSTICE PRATHIBA M. SINGH

O R D E R

% 16.01.2024 1.

This hearing has been done through hybrid mode. 2.

The present petition has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of mandate of the Sole Arbitrator. Ld. Counsel for the Petitioner submits that there are a total of four petitions, which have been filed by him. The arbitral proceedings are at the final stage and the arguments have been heard. 3.

For the reasons stated in the petition, the mandate of the Sole Arbitrator is extended till 30th May, 2024.

Let the final hearing be concluded and the award be passed by the next date of hearing. 4.

The petition is disposed of.

All pending applications are also disposed of.

PRATHIBA M. SINGH, J.

JANUARY 16, 2024/dk/bh The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 18/05/2024 at 11:37:57