High Court of DelhiO.M.P./302/2010
M/S Jog Engineering Ltd & B.G Shirke Construction Technology Pvt Ltd v. Mumbai Jnpt Port Road Company Ltd
2017-01-18Hon'Ble Dr. Justice S.Muralidhar1 pages
$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI R-334 + OMP 302/2010 & IA 7248/2010 JOG ENGINEERING LTD & B.G. SHIRKE CONSTRUCTION TECHNOLOGY PVT LTD ..... Petitioner Through: None.
versus MUMBAI JNPT PORT ROAD COMPANY LTD ..... Respondent Through: None.
CORAM: JUSTICE S. MURALIDHAR
O R D E R
% 18.01.2017
1. None appears for the Petitioner. It seems that the Petitioner is not interested in pursuing the petition.
2. Accordingly, the petition is dismissed for non-prosecution. The pending application also stands dismissed. The restoration application will be entertained only if an appropriate affidavit is filed by the Petitioner in support thereof.
S. MURALIDHAR, J JANUARY 18, 2017 Rm