$~21 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 520/2019 & I.A. 17863/2019 NAVRANG INFRASTRUCTURE INC ..... Petitioner Through:

Counsel (appearance not given) versus RUDRA BUILDWELL HOMES PVT LTD ..... Respondent Through:

Mr.Anurag Sahay, Adv. for Applicant no.1

CORAM:

HON'BLE MR. JUSTICE V. KAMESWAR RAO

O R D E R

% 17.12.2019 This is a joint petition filed by the parties under Section 29A(4) of the Arbitration and Conciliation Act, 1996 for extension of time for the Arbitral Tribunal to complete the proceedings and render the award by a period of six months effective from 24th December, 2019. In view of the contents of the petition, the same is allowed. The period for Arbitral Tribunal to complete the proceedings and render the award is extended by a period of six months effective from 24th December, 2019.

The petition along with the connected application is disposed of. Dasti.

V. KAMESWAR RAO, J DECEMBER 17, 2019/bh