M/S Orchid Infrastructure Developers (P). Ltd. v. Five Star Construction Pvt. Ltd
$~13 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (COMM) 146/2019 & I.A. 5150/2019 M/S ORCHID INFRASTRUCTURE DEVELOPERS (P).
LTD.
.....Petitioner Through:
Ms. Adya Rao, Advocate versus FIVE STAR CONSTRUCTION PVT. LTD .....Respondent Through:
Ms.
Kawaljit Kochar, Senior Advocate with Mr.
Deepanshu, Mr. Shreyas Mehrotra, Mr. Utkarsh Vats and Mr.
Drouhn Garg, Advocates
CORAM:
HON'BLE MR. JUSTICE AMIT BANSAL
O R D E R
% 08.09.2025 1.
The parties were referred for mediation before the Delhi High Court Mediation and Conciliation Centre ("Mediation Centre") via order dated 29th April, 2025.
2.
The parties have arrived at a settlement before the Mediation Centre. 3.
The Settlement Agreement dated 29th August, 2025, (hereinafter "Settlement Agreement") has been placed on record and the same bears the signatures of the authorised representatives of the petitioner and the respondent.
4.
I have gone through the terms of the Settlement Agreement and find the same to be lawful.
O.M.P. (COMM) 146/2019 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/09/2025 at 12:09:04
5.
In terms of the settlement, the Registry is directed to release a sum of ₹45,00,000/- in favour of the respondent. The remaining amount along with accrued interest shall be released in favour of the petitioner. 6.
The parties shall remain bound by the terms of the Settlement Agreement.
7.
The petition along with pending application stands disposed of. AMIT BANSAL, J SEPTEMBER 8, 2025 ds O.M.P. (COMM) 146/2019 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 10/09/2025 at 12:09:04