Hero Motocorp Ltd v. Dinesh Kumar Kaushal Sole Propritor Of Dv Automobiles
$~55 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 110/2026 HERO MOTOCORP LTD .....Petitioner Through:
Mr. Rahul Malhotra, Mr. Rahul Saxena, Ms. Padamja Sharma & Mr.
Aryan Jha, Advs.
versus DINESH KUMAR KAUSHAL SOLE PROPRITOR OF DV AUTOMOBILES .....Respondent Through:
Ms. Lakshmi Kailasan, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R
% 08.05.2026 1.
This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made, however, contends that only a reasonable period be granted. 3.
In view of the above, the time period for conclusion of the proceedings is extended by six months from today. The intervening period is regularized.
4.
This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J MAY 8, 2026 'JK'
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 12/05/2026 at 12:25:52