Esteem Project Private Limited v. Brahmaputra Cracker And Polymer Limited
$~48 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 114/2026 ESTEEM PROJECT PRIVATE LIMITED .....Petitioner Through:
Ms. Ginny Jetley Rautray, Mr.
Dharmendra Rautray & Mr. Arnav Tandon, Advs.
versus BRAHMAPUTRA CRACKER AND POLYMER LIMITED .....Respondent Through:
Mr. Nishant Awana & Mr. Suraj Kundu, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
O R D E R
% 29.01.2026 1.
This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.
2.
Learned counsel for the respondent has no serious objection to the prayer made.
3.
In view of the above, the time period for conclusion of the proceedings is extended by six months.
4.
This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J JANUARY 29, 2026 'ha'
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/02/2026 at 12:11:34