← Library
High Court of DelhiO.M.P.(MISC.)(COMM.)/121/2026

Sembcorp Green Infra Private Limited v. Siemens Gamesa Renewable Power Private Limited

2026-01-30Hon'Ble Mr. Justice Avneesh Jhingan1 pages

$~35 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 121/2026, I.A.

2561/2026 & I.A.

2562/2026 SEMBCORP GREEN INFRA PRIVATE LIMITED .....Petitioner Through:

Ms. Manjula Baxla, Adv.

versus SIEMENS GAMESA RENEWABLE POWER PRIVATE LIMITED .....Respondent Through:

Ms.

Riya Kalra, Mr.

Tanay Chaturvedi, Ms. Navya Nanda & Mr.

Paritosh, Advs.

CORAM:

HON'BLE MR. JUSTICE AVNEESH JHINGAN

O R D E R

% 30.01.2026 1.

This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.

2.

Learned counsel for the respondent has no serious objection to the prayer made.

3.

In view of the above, the time period for conclusion of the proceedings is extended by twelve months as prayed for. 4.

This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J JANUARY 30, 2026/'JK'