← Library
High Court of DelhiCONT.CAS(C)/18/2014

Surjeet Singh Saini & ORS v. Dr Rominder Kaur Randawa-Director Guru Tegh Bahadur Institute Of Technology & ORS

2018-07-19Hon'Ble Mr. Justice Siddharth Mridul2 pages

$~3 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ CONT.CAS(C) 18/2014 & CM APPL.29948/2015, CM APPL.28285/2018 SURJEET SINGH SAINI & ORS ..... Petitioners Through:

Mr. Shankar Raju and Mr. Nilansh Gaur, Advocates versus DR ROMINDER KAUR RANDAWA-DIRECTOR GURU TEGH BAHADUR INSTITUTE OF TECHNOLOGY & ORS ..... Respondents Through:

Mr. Abinash K. Mishra and Mr.

Nitish Harsh Gupta, Advocates for R-1 & R-2

CORAM:

HON'BLE MR. JUSTICE SIDDHARTH MRIDUL

O R D E R

% 19.07.2018 Mr. Abinash K. Mishra, learned counsel appearing on behalf of respondents No.1 and 2 states that they have complied with the directions given by this Court vide order dated 31.07.2013, inasmuch as, the payment to the petitioners including arrears, have been made on 26.08.2017 and 08.10.2015, respectively amounting to Rs.41,90,533/-. Insofar as, the interest thereon is concerned, learned counsel appearing on behalf of respondents No.1 and 2 undertakes to pay the same to the petitioners by the end of December, 2018. The undertaking is accepted.

CONT.CAS.(C) 18/2014

Insofar as, formulation of a promotion policy is concerned, it is stated that the same has been formulated by the respondents No.1 and 2 and forwarded to respondent No.3; and that the same shall be done within eight weeks from today.

Directed accordingly.

With the above directions, the petition is disposed of leaving the respondents No.1 and 2 to comply with their undertaking hereinabove, without demur. The pending applications also stand disposed of. SIDDHARTH MRIDUL, J JULY 19, 2018 dn CONT.CAS.(C) 18/2014