← Library
High Court of DelhiO.M.P. (E) (COMM.)/4/2024

Quality Engineers And Contractors v. Dy Chief Electrical Engineer Contructions

2024-02-01Hon'Ble Mr. Justice Prateek Jalan1 pages

$~23 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P. (E) (COMM.) 4/2024 & I.As. 2399-2400/2024 QUALITY ENGINEERS AND CONTRACTORS ..... Petitioner Through:

Mr. Vishwendra Verma & Mr.

Archit Verma, Advocates.

versus DY CHIEF ELECTRICAL ENGINEER CONTRUCTIONS ..... Respondent Through:

None.

CORAM:

HON'BLE MR. JUSTICE PRATEEK JALAN

O R D E R

% 01.02.2024 1.

Mr. Vishwendra Verma, learned counsel for the petitioner, states that this petition has been rendered infructuous as the arbitral award has already been passed.

2.

The petition is dismissed as withdrawn with liberty to the petitioner to raise all contentions available to it, in proceedings under Section 34 of the Arbitration and Conciliation Act, 1996.

3.

All pending applications also stand disposed of. PRATEEK JALAN, J FEBRUARY 1, 2024 'pv'/ The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 02/08/2024 at 12:44:45