M/S Manish Buildwell v. Delhi Technological University
$~52 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 104/2025 & I.A. 2621/2025 M/S MANISH BUILDWELL .....Petitioner Through:
Ms. Renuka Arora, Adv.
versus DELHI TECHNOLOGICAL UNIVERSITY .....Respondent Through:
Ms. Avnish Ahlawat, Ms. Palak Rohmitra & Mr. Mohnish Sehrawat, Advs.
CORAM:
HON'BLE MR. JUSTICE ANISH DAYAL
O R D E R
% 31.01.2025 1.
This petition has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 ('A&C Act') seeking extension of time for conclusion of arbitral proceedings and passing of arbitral award by the Sole Arbitrator.
2.
Arbitration proceedings commenced on 08th December 2022 and has proceeded since then. On 07th October 2024, parties mutually agreed for a six months' extension with effect from 3rd August 2024. Same is expiring on 2nd February 2025. Hence, this petition has been filed. 3.
Respondent has no objection to further extension of time for arbitral proceedings to continue.
4.
Petitioner's counsel submits that cross examination of witnesses is yet to conclude, and counter claim by respondent also needs to be considered.
5.
Accordingly, extension for a period of 10 months is granted for conclusion of arbitral proceedings.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 06/02/2025 at 14:49:33
6.
Petition stands disposed of with these directions. Pending application is rendered infructuous.
7.
Order be uploaded on the website of this Court. ANISH DAYAL, J JANUARY 31, 2025/sm/sc The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 06/02/2025 at 14:49:33