Guruvayoor Infrastructure Private Limited v. National Highway Authority Of India
$~32 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 125/2025 GURUVAYOOR INFRASTRUCTURE PRIVATE LIMITED .....Petitioner Through:
Mrs. Smiti Verma, Mr. Pranay Chitale, Mr. Dhruv Bhalla, Advocates versus NATIONAL HIGHWAY AUTHORITY OF INDIA .....Respondent Through:
Mr. Ankur Mittal and Mr. Ashish Gajwani, Advocates
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
O R D E R
% 07.02.2025 I.A. 3243/2025 (Exemption) Allowed, subject to all just exceptions.
O.M.P.(MISC.)(COMM.) 125/2025 1.
This is a petition under Section 29A (5) of the Arbitration & Conciliation Act, 1996 seeking extension of mandate of the Arbitral Tribunal for making the arbitral award.
2.
Material on record indicates that disputes arose between the parties under the Concession Agreement dated 27.03.2006 and an Arbitral Tribunal was constituted which entered into Reference on 18.07.2020. 3.
It is stated that the mandate of the Arbitral Tribunal has been extended from time to time and last of such extension was granted on 12.12.2023 till 18.12.2024. It is stated that since the mandate of the Arbitral Tribunal has The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 13/02/2025 at 12:50:04
come to an end on 18.12.2024, the Petitioner has approached this Court seeking extension of mandate of the Arbitral Tribunal. 4.
Learned Counsel for the Respondent states that the Respondent does not have any objection for the extension of the mandate. 5.
The Apex Court in Rohan Builders (India) Private Limited v. Berger Paints India Limited, 2024 SCC OnLine SC 2494, has held that an application for extension of the time period for passing an arbitral award under Section 29A(4) read with Section 29A(5) is maintainable even after the expiry of the twelve-month or the extended six-month period, as the case may be.
6.
In view of the facts and circumstances of the case, this Court is inclined to extend the mandate of the Arbitral Tribunal till 28.02.2026 to enable the Arbitral Tribunal to proceed further in the matter. Further, the period from 18.12.2024 till today is regularised. 7.
The petition is disposed of along with the pending applications, if any. SUBRAMONIUM PRASAD, J FEBRUARY 07, 2025 hsk The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 13/02/2025 at 12:50:04