$~47 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 176/2026 FEEDBACK INFRA PRIVATE LIMITED THROUGH ITS RESOLUTION PROFESSIONAL RAJNEESH KUMAR AGARWAL .....Petitioner Through:

Mr. Abhishek Anand, Mr. Karan Kohli, Ms. Palak Kalra & Ms. Arshita Girdha, Advs. (through VC) versus NATIONAL HIGHWAY INFRASTRUCTURE DEVELOPMENT CORPORATION LTD .....Respondent Through:

Mr. Aditya Chandra, Adv. (through VC) with Mr. Rahul Chaudhary & Mr. Durga Dass Vashist, Advs.

CORAM:

HON'BLE MR. JUSTICE AVNEESH JHINGAN

O R D E R

% 17.02.2026 1.

This petition is filed under Section 29A of the Arbitration & Conciliation Act, 1996 seeking extension of period for concluding the arbitration proceedings.

2.

Learned counsel for the respondent has no serious objection to the prayer made.

3.

In view of the above, the time period for conclusion of the proceedings is extended by one year as prayed for. 4.

This petition is disposed of in the aforesaid terms. AVNEESH JHINGAN, J FEBRUARY 17, 2026 'ha'

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 19/02/2026 at 12:51:45