Mbl Infrastructure Ltd v. Pradeep Colonisers And Suppliers Pvt Ltd
$~81 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 138/2025 MBL INFRASTRUCTURE LTD .....Petitioner Through:
Ms. Anusuya Salwan, Mr. Rachit Wadhwa and Mr. Bankim Garg, Advocates.
versus PRADEEP COLONISERS AND SUPPLIERS PVT LTD .....Respondent Through:
Mr. Rahul Sinha, Advocate
CORAM:
HON'BLE MR. JUSTICE MANOJ KUMAR OHRI
O R D E R
% 12.02.2025 I.A. 3628/2025 (exemption) 1.
Allowed, subject to all just exceptions.
2.
The application stands disposed of.
O.M.P.(MISC.)(COMM.) 138/2025 1.
By way of the present petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 ('A&C Act'), the petitioner seeks extension of mandate of the Arbitral Tribunal by a period of nine months for concluding the Arbitral proceedings and passing the Award. 2.
Learned counsel for the petitioner submits that the mandate of the Arbitral Tribunal has expired on 12.02.2025.
3.
Issue notice.
4.
Learned counsel appears on behalf of the respondents on advance copy, accepts notice and submits that the respondent has no objection to the prayer made in the petition.
5.
Considering the aforesaid request and the no objection given by the other side, the present petition is allowed and the mandate of the Arbitral The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 15/02/2025 at 12:09:20
Tribunal for passing of the award is extended by a period of nine month from today.
6.
The present petition is disposed of.