High Court of DelhiO.M.P.(MISC.)(COMM.)/31/2019

Team Infrastructure Private Limited v. A.G International

2019-01-24Hon'Ble Mr. Justice Navin Chawla2 pages

$~15 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 31/2019 TEAM INFRASTRUCTURE PRIVATE LIMITED ..... Petitioner Through: Mr.Prateek Gupta, Mr.J.Krishna Dev, Advs.

versus A.G INTERNATIONAL ..... Respondent Through: Mr.Surender Chauhan, Mr.Vikas Saini, Advs.

CORAM:

HON'BLE MR. JUSTICE NAVIN CHAWLA

O R D E R

% 24.01.2019 IA 1019/2019 Exemption allowed subject to all just exceptions. OMP(Misc.)(Com.) 31/2019 1.

This petition has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of time for the Sole Arbitrator to pass the Award.

2.

Counsel for the respondent who appears on an advance notice submits that the respondent has no objection if the time for making of the Award is extended by this Court. He submits that the respondent has also made a counter claim in the arbitration proceedings. 3.

Having perused the contents of the petition and no objection expressed by the respondent, the time for making of the Award by the Sole Arbitrator is extended by a further period of one month with effect from 31.01.2019.

4.

The petition is allowed in the above terms with no order as to cost.

Dasti.

NAVIN CHAWLA, J JANUARY 24, 2019 RN