High Court of DelhiO.M.P.(I) (COMM.)/80/2023

Mrs. Shikha Saxena & ANR. v. Almond Infrabuild Pvt Ltd & ORS.

2024-08-27Hon'Ble Mr. Justice C.Hari Shankar2 pages

$~39 *

IN THE HIGH COURT OF DELHI AT NEW DELHI

+ O.M.P.(I) (COMM.) 80/2023 and IA 37389/2024 and 37390/2024 MRS. SHIKHA SAXENA & ANR.

.....Petitioners Through:

Mr Nikhil Joshi, Ms. Kashish Bansal and Mr Archit Relan, Advocates versus ALMOND INFRABUILD PVT LTD & ORS. .....Respondent Through:

Mr. Nishant Kumar, Advocate

CORAM:

HON'BLE MR. JUSTICE C.HARI SHANKAR

O R D E R

% 27.08.2024 1.

The disputes between the parties stand settled. The settlement agreement dated 10 April 2024 is on record.

2.

The petitioner has moved an application under Order 1 Rule 10 CPC to implead M/s ATS Infrastructure Ltd as Respondent 4. 3.

As M/s ATS Infrastructure Ltd is a necessary party to the settlement, the request is acceded to. M/s ATS Infrastructure Ltd shall stand impleaded as Respondent 4. The parties are represented by their respective counsel. The learned counsel for the parties undertake on behalf of their clients to remain bound by the terms of settlement. The Court has perused the terms of settlement and find them to be in order. As such, dispute does not survive for consideration. OMP(I)(COMM) 80/2023 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/08/2024 at 12:30:05

4.

The petition is disposed of in terms of the settlement agreement dated 10 April 2024.

C.HARI SHANKAR, J AUGUST 27, 2024/yg Click here to check corrigendum, if any OMP(I)(COMM) 80/2023 The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/08/2024 at 12:30:05