Fasal v. Municipal Corporation Of Delhi And ORS.
$~A-23 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 3298/2023 & CM APPLs.12824/2023 and 22292/2023 FASAL .....Petitioner Through:
Mr.Harshit Gupta, Advocate (through VC).
versus MUNICIPAL CORPORATION OF DELHI AND ORS.
.....Respondents Through:
Ms.Richa Dhawan, Advocate with Mr.Anuj Chaturvedi, Standing Counsel for R-1.
Mr.Santosh Kr.Tripathi, SC (Civil) with Mr.Kartik Sharma, Advocate for R-2.
Mr.Anees Ahmad, Advocate with MD Miskeen, Advocate for R-4.
CORAM:
HON'BLE THE ACTING CHIEF JUSTICE HON'BLE MR. JUSTICE TUSHAR RAO GEDELA
O R D E R
% 08.07.2024 1.
Learned counsel for the Petitioner states that he has instructions to withdraw the present writ petition.
2.
Learned counsel for the Respondent No.1-MCD states that partial demolition action has already been taken. He assures and undertakes to this Court that the balance demolition shall be undertaken on 12th July, 2024. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 22/07/2024 at 12:33:25
3.
Recording the aforesaid statement and holding the Respondent No.1MCD bound by the same, the present writ petition stands disposed of. ACTING CHIEF JUSTICE TUSHAR RAO GEDELA, J JULY 8, 2024/TS The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 22/07/2024 at 12:33:25