M/S S.S.Total Construction (India) Pvt. Ltd. v. All India Institute Of Medical Sciences (Aiims)
$~O-38 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(MISC.)(COMM.) 29/2020 M/S S.S.TOTAL CONSTRUCTION (INDIA) PVT. LTD.
..... Petitioner Through:
Mr.Mohinder Kumar Madan and Ms.Renuka, Advocates versus ALL INDIA INSTITUTE OF MEDICAL SCIENCES (AIIMS) ..... Respondent Through:
Mr.V.S.R.Krishna and Mr.V.Shashank Kumar, Advocates
CORAM:
HON'BLE MR. JUSTICE J.R. MIDHA
O R D E R
% 21.01.2020 IA No.841/2020 Allowed subject to just exceptions.
OMP (MISC.) (COMM.) No.29/2020 Issue notice.
Learned counsel for the respondent accepts notice. The parties are jointly seeking extension of time for conclusion of arbitration proceedings.
The arbitration proceedings are at the stage of recording of respondent's evidence.
The petition is allowed and the time period for conclusion of arbitration proceedings is extended with effect from 27th December, 2019 for a further period of six months from today.
Copy of this order be given dasti to learned counsel for the parties under signatures of the Court Master. J.R. MIDHA, J.
JANUARY 21, 2020/mamta