Promax Power Ltd. v. Tahal Consulting Engineers (I) Pvt. Ltd.
$~25 *
IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(I) (COMM.) 73/2024 & I.A. 7630/2024 PROMAX POWER LTD.
..... Petitioner Through:
Mr. Vinit Trehan & Mr. Yash Srivastava, Advocates.
versus TAHAL CONSULTING ENGINEERS (I) PVT. LTD.
..... Respondent Through:
Mr. Kamal Mehta, Mr. Abhishek Chauhan, Advocates alongwith AR of the Company.
CORAM:
HON'BLE MR. JUSTICE PRATEEK JALAN
O R D E R
% 15.05.2024 1.
This petition under Section 9 of the Arbitration and Conciliation Act, 1996 ["the Act"] has been filed for interim measures of protection in respect of the amount awarded to the petitioner under an arbitral award dated 31.01.2024. Learned counsel state that proceedings under Section 34 of the Act have been filed by the respondent, and an enforcement petition has already been filed by the petitioner. 2.
The petition is therefore disposed of, without prejudice to the rights and contentions of the petitioner in the enforcement proceedings. All remedies available to the petitioner are left open. 3.
The petition, alongwith pending application, stands disposed of. PRATEEK JALAN, J MAY 15, 2024/'pv'/ The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 03/07/2025 at 04:09:35